Updated every 15 minutes · From ODOT
Ohio road construction today
Every work zone the Ohio Department of Transportation has in force today, by highway: lane closures, full closures and how long they last, on I-71, I-75, I-70, I-90, I-77 and every state highway.
562 work zones today · 156 full closures
Interstates
I-70 10 work zones
- Road closedWestboundI-70 westbound between I-71 and SR 315 will close starting 10 p.m. Friday, October 30 through 5 a.m. Monday, November 2.until Nov 2
- Road closedWestboundI-70 westbound between I-71 and SR 315 will close starting 10 p.m. Friday, October 30 through 5 a.m. Monday, November 2.until Nov 2
- Lanes closedEastboundMotorist can expect intermittent lane closures for repairs. (IR 70)until Nov 13
- Lanes open, work nearbyWestboundI-70 WB passing lane operates like an express lane. This means that once motorists enter the express lane after SR 93 (exit 157), they will be unable to exit until U.S. 40 (exit 152). (IR 70)until Oct 17
- Lanes closedWestboundMotorist can expect intermittent lane closures for repairs. (IR 70)until Nov 13
- Lanes open, work nearbyEastboundLane shifts for construction at the I-70/SR 149 (EXIT 208) interchange improvement project. Two lanes of traffic are maintained with a 12-foot width restriction. (IR 70)until May 31
- Lanes closedEastboundI-70 eastbound between the Madison County Line and Hilliard Rome Road will be reduced to one lane overnight (8 p.m. - 6 a.m.) Friday, October 9. (IR70)until Jul 1
- Lanes closedEastboundI-70 eastbound between the Madison County Line and Hilliard Rome Road will be reduced to one lane overnight (8 p.m. - 6 a.m.) Friday, October 9. (IR70)until Jul 1
- Road closedEastboundThe Maple Avenue flyover ramp to I-70 EB is closed to traffic. (RAMP FROM CR 2022 MAPLE AVE TO IR 70)until Oct 31
- Road closedSouthboundThe SR 315 southbound ramp to I-70 eastbound will close starting 10 p.m. Friday, May 17, 2024, for multiple years. (RAMP FROM RA 25532 TO IR 70)until Jun 1
I-71 10 work zones
- Road closedSouthboundThe I-70 westbound to I-71 southbound (flyover) ramp will close starting 10 p.m. Friday, October 30 through 5 a.m. Monday, November 2.until Nov 2
- Lanes closedNorthboundI-71 from the Ashland County line to SR 13 will have single lane closures for a resurfacing project. Nightly lane closures will begin Sunday, May 17 from 7:00 p.m. to 6:00 a.m. for resurfacing work. There will only be daytime lane closures, when necessary, but majority of daytime work will be along the shoulder and in the median. (IR 71)until Nov 6
- Lanes closedSouthboundI-71 from the Ashland County line to SR 13 will have single lane closures for a resurfacing project. Nightly lane closures will begin Sunday, May 17 from 7:00 p.m. to 6:00 a.m. for resurfacing work. There will only be daytime lane closures, when necessary, but majority of daytime work will be along the shoulder and in the median. (IR 71)until Nov 6
- Road closedSouthboundThe I-70 westbound to I-71 southbound (flyover) ramp will close starting 10 p.m. Friday, October 30 through 5 a.m. Monday, November 2. (IR71)until Nov 2
- Lanes closedNorthboundReplacement of the pedestrian bridge over I-71 and I-471, between VanMeter Street and Gilbert Avenue, and replacement of the pedestrian bridge over Gilbert Avenue (U.S. 22). The project also includes construction of a new shared use path bridge over I-71, I-471 and U.S. 22, and construction of a new stairway. Traffic on I-71 and I-471 will be maintained; however, Gilbert Avenue will be subject to (IR71 EXPY)until Dec 31
- Lanes closedEastboundThe I-77 northbound ramps to I-480 will have various lane restrictions through December. (RAMP FROM IR 71 TO IR 480)until Dec 1
- Road closedNorthboundAs part of the Brent Spence Bridge Corridor Project, the ramp from I-71 North to Second Street will be closed for demolition and reconstruction. The closure will go into effect July 16, 2026, and will remain in effect through late fall of 2028. Motorists will be detoured by way of I-75 North to the Fifth Street exit (Exit 1C) and Race Street to Second Street. (RAMP FROM IR 71 TO MR 8628 ELM ST)until Dec 16
- Lanes closedNorthboundThe I-71 northbound ramp to U.S. 36/SR 37 will be reduced to one lane starting Wednesday, April 8 through Fall 2026. (RAMP FROM IR 71 TO US 36)until Nov 15
- Lanes open, work nearbyWestboundThe I-71 northbound ramps to I-480 will have various lane restrictions through December. (RAMP FROM RA 18048 TO IR 480N)until Dec 1
- Lanes open, work nearbyWestboundI-71 northbound to I-480 westbound will be reduced to one lane beginning Thursday, April 2, through July 2028. (RAMP FROM RA 18048 TO IR 480N)until Dec 1
I-75 38 work zones
- Lanes closedEastboundThe South GMR walk between I-75 and SR 48 will be closed for approximately 100 days starting Wednesday, June 24. Crews will be installing lighting, pedestrian accommodations, and path upgrades. The paved levee walk will remain open during this work. River Walk users will follow the signed detour. (GREAT MIAMI RIVER TRAIL)until May 1
- Lanes open, work nearbyNorthboundPhase 8B of the Mill Creek Expressway Project. Project will construct a new Pump Station and Combined Sewer Overflow for the widening of IR 75. Phases 8+8C widen for additional through lanes, rehabilitate existing pavement and bridges. Reconstruct SR 56 2 interchange, remove the Towne Ave. interchange, complete minor improvements to the Paddock Road interchange, and tie into the existing SR 126 in (I-75 NB EXPY)until Dec 31
- Lanes open, work nearbyNorthboundEarly Monday, September 14, Northbound I-75 will be back to three travel lanes, but will remain shifted to the exterior/outside. Southbound I-75 will remain in its current pattern. This pattern is expected to remain (INTERSTATE 75)until Nov 16
- Lanes open, work nearbySouthboundExpect intermittent shoulder restrictions on I-75 between Lyons Road and Pennyroyal Road while crews install temporary lighting. (IR 75)until Nov 6
- Lanes closedNorthboundInterstate 75, in Lucas County between the Michigan state line and the Maumee River, will experience left lane restrictions and shoulder closures for drain cleaning beginning Monday, October 19 through October. (IR 75)until Nov 13
- Lanes open, work nearbyNorthboundDuring the shift, motorists traveling North on I-75 will not have access to the entrance or exit ramps at Austin Landing Boulevard and the interchange at I-75/I-675. This work is expected to be completed by mid-morning, Saturday, July 25, and access will (IR 75)until May 31
- Lanes closedSouthboundA longitudinal joint repair project on I-75 North and South, between S.R. 129 in Butler County and Pennyroyal Road in Warren County. Traffic will be maintained in a minimum of one, 12-foot lane in either direction during late evening and overnight hours. (IR 75)until Oct 3
- Lanes closedNorthboundI-75 in both directions will be subject to overnight lane restrictions between Lyons Road and Pennyroyal Road from 7:30 p.m. through 5 a.m. starting Friday, July 31through November 2026. (IR 75)until Nov 6
- Lanes closedNorthboundInterstate 75, in Lucas County between the Michigan state line and the Maumee River, will experience left lane restrictions and shoulder closures for drain cleaning beginning Monday, October 19 through October. (IR 75)until Nov 13
- Lanes closedNorthboundInterstate 75, in Lucas County between the Michigan state line and the Maumee River, will experience left lane restrictions and shoulder closures for drain cleaning beginning Monday, October 19 through October. (IR 75)until Nov 13
I-76 3 work zones
- Lanes closedWestboundNEW IMPACT – Beginning Monday, June 1, I-80 east and west will be reduced to two lanes between the Meander Reservoir and SR 46 with traffic shifted to the outside shoulder and right lane. (IR 76)until Nov 14
- Lanes closedEastboundNEW IMPACT – Beginning Monday, June 1, I-80 east and west will be reduced to two lanes between the Meander Reservoir and SR 46 with traffic shifted to the outside shoulder and right lane. (IR 76)until Nov 14
- Lanes closedEastboundNEW IMPACT – Beginning Monday, June 1, I-80 east and west will be reduced to two lanes between the Meander Reservoir and SR 46 with traffic shifted to the outside shoulder and right lane. (IR 76)until Nov 14
I-77 4 work zones
- Lanes open, work nearbySouthboundI-77 northbound and southbound between Ghent Rd. and Everett Rd. is reduced to two lanes through early summer 2026. (IR 77)until Nov 30
- Lanes closedNorthboundThe ramp from I-77 northbound to I-277/U.S. 224 westbound is reduced to one lane through early August. (RAMP FROM IR 77 TO IR 277N)until Nov 20
- Road closedNorthboundThe I-77 northbound exit to E. 22nd/E.14th St. will be closed beginning Monday, July 13, through December. (RAMP FROM IR 77 TO MR 2514 E 14TH ST)until Dec 10
- Road closedEastboundThe I-77 northbound exit to E. 22nd/E.14th St. will be closed beginning Monday, July 13, through December. (RAMP FROM RA 18437 TO RA 18439)until Dec 10
I-80 1 work zone
- Lanes closedWestboundNEW IMPACT – Beginning Monday, June 1, I-80 east and west will be reduced to two lanes between the Meander Reservoir and SR 46 with traffic shifted to the outside shoulder and right lane. (IR 80)until Nov 14
I-90 17 work zones
- Lanes closedWestboundI-90 under King Memorial Rd. will have various lane closures through November. (IR 90)until Nov 20
- Lanes closedWestboundI-90 between SR 306 and Paine Rd. will have various nightly lane restrictions through November. (IR 90)until Nov 30
- Lanes closedEastboundI-90 between SR 306 and Paine Rd. will have various nightly lane restrictions through November. (IR 90)until Nov 30
- Lanes closedEastboundI-90 under King Memorial Rd. will have various lane closures through November. (IR 90)until Nov 20
- Lanes closedEastboundI-90 EB between E. 14th St. and Prospect Ave. will have various lane restrictions through November (IR 90)until Nov 23
- Lanes closedEastboundI-90 in Lake County will have various lane and shoulder closures through November. (IR 90)until Nov 15
- Lanes closedWestboundI-90 in Lake County will have various lane and shoulder closures through November. (IR 90)until Nov 15
- Lanes closedWestboundI-90 EB between E. 14th St. and Prospect Ave. will have various lane restrictions through November (IR 90)until Nov 23
- Lanes open, work nearbyWestboundI-90 between West Blvd. and Hillard Blvd. has various lane restrictions, short duration ramp closures, and lane shifts through Fall 2028. (IR 90)until May 31
- Lanes open, work nearbyWestboundI-90 westbound between Maplegrove Rd. and I-271 will be maintained via lane shifts and shoulder closures beginning Monday, October 13, through May 2027. (IR 90)until May 25
I-271 4 work zones
- Lanes open, work nearbyNorthboundThe I-271 Local Lanes under U.S. 6 will have daily lane restrictions through July 2027 for overhead work. (IR 271)until Nov 13
- Lanes open, work nearbySouthboundThe I-271 Local Lanes under U.S. 6 will have daily lane restrictions through July 2027 for overhead work. (IR 271)until Nov 13
- Lanes open, work nearbySouthboundThe I-271 Express Lanes under U.S. 6 will have daily lane restrictions through July 2027 for overhead work. (IR 271X)until Nov 13
- Lanes open, work nearbySouthboundThe I-271 Express Lanes under U.S. 6 will have daily lane restrictions through July 2027 for overhead work. (IR 271X)until Nov 13
I-275 4 work zones
- Lanes open, work nearbyNorthboundA bridge rehabilitation project on Branch Hill Miamiville Road over I-275. Traffic on I-275 will be maintained with shoulder closures and periodic lane closures. Branch Hill Miamiville Road is closed through mid-September 2026. (IR 275)until Aug 1
- Lanes closedEastboundA 16-foot height restriction will be in effect on the Branch Hill Miamiville Road bridges over I-275. Traffic on I-275 will be maintained through the work zone. (IR 275)until Nov 21
- Lanes closedWestboundA 16-foot height restriction will be in effect on the Branch Hill Miamiville Road bridges over I-275. Traffic on I-275 will be maintained through the work zone. (IR 275)until Nov 21
- Lanes open, work nearbySouthboundA bridge rehabilitation project on Branch Hill Miamiville Road over I-275. Traffic on I-275 will be maintained with shoulder closures and periodic lane closures. Branch Hill Miamiville Road is closed through mid-September 2026. (IR 275)until Aug 1
I-277 1 work zone
- Lanes closedEastboundBeginning Thursday morning, June 4, I-277/U.S. 224 over I-77 will be reduced to one lane in each direction for bridge repairs. (IR 277)until Nov 13
I-480 4 work zones
- Lanes open, work nearbyEastboundI-480 eastbound and westbound over Stow Rd. has various lane restrictions. (IR 480)until Nov 13
- Lanes open, work nearbyWestboundI-480 eastbound and westbound over Stow Rd. has various lane restrictions. (IR 480)until Nov 13
- Lanes open, work nearbyEastboundI-480 under I-71 will have various lane restrictions through December for overhead work. (IR 480)until Dec 1
- Lanes open, work nearbyWestboundThe I-71 northbound ramps to I-480 will have various lane restrictions through December. (IR 480)until Dec 1
I-490 2 work zones
- Lanes closedEastboundI-490 eastbound between I-90 and I-77 is in a bi-directional traffic pattern through November. All traffic wishing to access I-77 must stay in the right lane. All traffic wishing to access Opportunity Corridor Blvd. needs to stay in the left lane. (IR 490)until Nov 8
- Road closedEastboundI-490 east exit ramp to Broadway Ave. will be closed through fall 2027. (RAMP FROM IR 490 TO SR 14 BROADWAY AVE)until Oct 31
I-680 5 work zones
- Lanes closedNorthboundBeginning Monday, April 13, I-680 northbound between South Ave. and SR 193 will be closed through summer 2027. The detour will be US 62 to US 422 to SR 193. (IR 680)until Aug 31
- Lanes closedSouthboundBeginning Monday, April 13, I-680 northbound between South Ave. and SR 193 will be closed through summer 2027. The detour will be US 62 to US 422 to SR 193. (IR 680)until Aug 31
- Road closedNorthbound• Marshall St. to I-680 north. The detour will be Glenwood Ave. to Mahoning Ave. to Belle Vista Ave. (RAMP FROM MR 1232 ROCKVIEW AVE TO IR 680N I680)until Aug 31
- Road closedNorthbound• Woodland Ave. to I-680 north. The detour will be Woodland Ave. to Hadnet Dr. to South Ave. to U.S. 62/SR 7 to U.S. 422 to SR 193. (RAMP FROM MR 2200 W WOODLAND AVE TO IR 680N I680)until Aug 31
- Road closedNorthbound• Market St. to I-680 north. Th detour will be Woodland Ave. to Hadnet Dr. to South Ave. to U.S. 62/SR 7 to U.S. 422 to SR 193. (RAMP FROM US 62N EAST RIVER CROSSING TO IR 680N I680)until Aug 31
US highways
US-6 7 work zones
- Road closedEastboundU.S. 6 over I-271 has various lane restriction through July 2027. (CHARDON RD)until Jul 1
- Road closedWestboundU.S. 6 over I-271 has various lane restriction through July 2027. (CHARDON RD)until Jul 1
- One lane, alternatingWestboundThe U.S. 6 Connectivity Corridor is from Cedar Point Drive in the city of Sandusky through the SR 2 interchange with Rye Beach Road to the city of Huron. Crews are beginning embankment work at the U.S. 6/Perkins Ave intersection outside the existing roadway alignment. Traffic will be maintained at all times utilizing flaggers and/or temporary traffic signals during working hours only. The full clo (CLEVELAND RD)until Jun 1
- One lane, alternatingEastboundThe U.S. 6 Connectivity Corridor is from Cedar Point Drive in the city of Sandusky through the SR 2 interchange with Rye Beach Road to the city of Huron. Crews are beginning embankment work at the U.S. 6/Perkins Ave intersection outside the existing roadway alignment. Traffic will be maintained at all times utilizing flaggers and/or temporary traffic signals during working hours only. The full clo (CLEVELAND RD)until Jun 1
- Road closedEastboundThe SR 2 eastbound exit ramp to Rye Beach Road (Exit 142) will close Monday, September 21 to construction the legs of the future roundabout at the Rye Beach Road interchange and reconstruct the exit ramp. (RAMP FROM SR 2 TO US 6)until Dec 19
- Road closedWestboundThe Rye Beach Road entrance ramp to SR 2 westbound will close Monday, September 21 to construct the legs of the future roundabout at Rye Beach Road interchange and reconstruct the entrance ramp. (RAMP FROM US 6 CLEVELAND RD TO SR 2N)until Dec 19
- Road closedWestboundWestbound U.S. 24, between State Route 109 and the Defiance County Line, is closed for reconstruction. All traffic is shifted to the eastbound 24 lanes for the duration of the closure. Crossovers will be in place at all exits across the westbound lanes within work zone limits, except at the U.S. 6 interchange where all ramps to/from westbound are closed. (US 6)until Jun 7
US-20 7 work zones
- Lanes closedSouthboundA resurfacing project in the city of Elyria along U.S. 20 (John F. Kennedy Memorial Parkway), from Chestnut Ridge Road to Cleveland Street, and along SR 301 (Abbe Road), from Kennedy Memorial Parkway to just north of Antioch Drive. Traffic will be maintained at all times. Night work will conitnue on U.S. 20 from Chestnut Ridge Road to Cleveland Street. (ABBE RD)until Nov 30
- Lanes closedNorthboundA resurfacing project in the city of Elyria along U.S. 20 (John F. Kennedy Memorial Parkway), from Chestnut Ridge Road to Cleveland Street, and along SR 301 (Abbe Road), from Kennedy Memorial Parkway to just north of Antioch Drive. Traffic will be maintained at all times. Night work will conitnue on U.S. 20 from Chestnut Ridge Road to Cleveland Street. (ABBE RD)until Nov 30
- Lanes closedEastboundA resurfacing project in the city of Elyria along U.S. 20 (John F. Kennedy Memorial Parkway), from Chestnut Ridge Road to Cleveland Street, and along SR 301 (Abbe Road), from Kennedy Memorial Parkway to just north of Antioch Drive. Traffic will be maintained at all times. Night work will conitnue on U.S. 20 from Chestnut Ridge Road to Cleveland Street. (CLEVELAND ST)until Nov 30
- Lanes closedEastboundU.S. 20 between Center Rd. and Lane Rd. will have various restrictions through December. (N RIDGE RD)until Dec 18
- Road closedWestboundWestbound U.S. Route 20 ramp to E. State St. (Exit 105) is closed during construction of a roundabout through December 1. Detour: Westbound US 20 to US 6 to N. 5th St. to Walnut St. to Ohio Ave. and vice versa. (RAMP FROM US 20N E STATE ST TO CR 20N E STATE ST)until Dec 1
- Road closedEastboundU.S. Route 20, between County Road 13-1 and County Road 14, over Bear Creek, will be closed for a culvert replacement beginning Wednesday, October 7 for approximately 30 days. Detour: US 20 to SR 108 to US 20A to SR 109 to US 20.until Nov 6
- Lanes closedWestboundWestbound US 20 will experience lane restrictions during construction of a roundabout at US 20/E. State St. (W MC PHERSON HWY)until Dec 1
US-22 5 work zones
- Road closedSouthboundA pavement rehabilitation/reconstruction project on Davids Drive, between Rombach Avenue (U.S. 22) and Lynne Lane in the city of Wilmington. Beginning Monday, August 17, Davids Drive will be closed for up to 90 days, and traffic will be detoured via Progress Way, Airbourne Road, S.R. 134 and Davids Drive. (DAVIDS DR)until Nov 30
- Road closedNorthboundA pavement rehabilitation/reconstruction project on Davids Drive, between Rombach Avenue (U.S. 22) and Lynne Lane in the city of Wilmington. Beginning Monday, August 17, Davids Drive will be closed for up to 90 days, and traffic will be detoured via Progress Way, Airbourne Road, S.R. 134 and Davids Drive. (DAVIDS DR)until Nov 30
- Road closedEastbound90-day ramp closure. Detour: Continue east on U.S. 22 to EXIT 224 (SR 151 west), take EXIT 224 to SR 151 east, SR 151 east to U.S. 22 west, continue west on U.S. 22 to return to EXIT 219 (Cadiz/U.S. 250 east/SR 9 north). (LINCOLN AVE)until Nov 8
- Lanes closedEastboundResurfacing between the Warren County line and the corporation limit of Wilmington. Preliminary work will begin the week of April 6 and continue through early May. Paving operations are scheduled tentatively to begin in mid-May. Throughout construction, traffic will be maintained in a minimum of one lane with the use of flaggers and/or traffic control devices. (US 22)until Nov 6
- Lanes closedEastboundWVDOT bridge repair project. One lane of traffic is maintained throughout construction. Expect possible delays. (US 22)until Dec 31
US-23 11 work zones
- Road closedWestboundCH4 will be closed east on US23 along with the median at the intersection of CH4 and US23 for 60 days (CR 4)until Dec 11
- Road closedEastboundCH4 will be closed east on US23 along with the median at the intersection of CH4 and US23 for 60 days (CR 4)until Dec 11
- Lanes closedNorthboundMay have temporary lane or shoulder closures for sign upgrades (US 23)until Nov 21
- Lanes closedSouthboundboth directions will be restricted to the right driving lane for work in the median. (US 23)until Nov 6
- Lanes closedSouthboundboth directions will be restricted to the right driving lane for work in the median. (US 23)until Nov 6
- Lanes closedNorthboundExpect lane closures on U.S. 23 between Debord Road and Maple Lane. (US 23)until Nov 13
- Lanes closedNorthboundRoadway maintenance on U.S. 23 between Alma Omega Road and Woodland Park Road. (US 23)until Nov 14
- Lanes closedNorthboundboth directions will be restricted to the right driving lane for work in the median. (US 23)until Nov 6
- Lanes closedSouthboundMay have temporary lane or shoulder closures for sign upgrades (US 23)until Nov 21
- Lanes closedNorthboundboth directions will be restricted to the right driving lane for work in the median. (US 23)until Nov 6
US-24 2 work zones
- Road closedWestboundWestbound U.S. 24, between State Route 109 and the Defiance County Line, is closed for reconstruction. All traffic is shifted to the eastbound 24 lanes for the duration of the closure. Crossovers will be in place at all exits across the westbound lanes within work zone limits, except at the U.S. 6 interchange where all ramps to/from westbound are closed. (US 24)until Jun 7
- Road closedWestboundWestbound U.S. 24, between State Route 109 and the Defiance County Line, is closed for reconstruction. All traffic is shifted to the eastbound 24 lanes for the duration of the closure. Crossovers will be in place at all exits across the westbound lanes within work zone limits, except at the U.S. 6 interchange where all ramps to/from westbound are closed. (US 24)until Jun 7
US-30 10 work zones
- Road closedWestboundThe SR 11 northbound ramp and the U.S. 30 westbound ramp are closed at this location for construction. Additionally, U.S. 30 westbound under SR 11 is closed. (EAST LIVERPOOL RD)until Nov 13
- Lanes closedWestboundtruck parking area is closed for truck parking expansion project (RAMP FROM US 30 N TO US 30 N)until Dec 1
- Lanes closedEastboundtruck parking area is closed for truck parking expansion project (RAMP FROM US 30 TO US 30)until Dec 1
- Lanes closedWestboundMay have temporary lane or shoulder closures for sign upgrades (US 30)until Nov 21
- Road closedWestboundThe SR 11 northbound ramp and the U.S. 30 westbound ramp are closed at this location for construction. Additionally, U.S. 30 westbound under SR 11 is closed. (US 30)until Nov 13
- Lanes closedWestboundrestricted to one lane, total width 16 feet (12' lane with 2'shoulders) (US 30)until Nov 4
- Lanes closedEastboundMay have temporary lane or shoulder closures for sign upgrades (US 30)until Nov 21
- Lanes closedEastboundrestricted to one lane, total width 16 feet (12' lane with 2'shoulders) (US 30)until Nov 4
- Lanes closedEastboundU.S. 30 at the east and west bridges over the Norfolk Southern Railroad, just west of SR 98, will be reduced to one lane of traffic in each direction for a bridge replacement project. On Wednesday, May 20 traffic will be switched into a new pattern using the median crossovers. One 11’ lane in each direction will be maintained on the westbound side of the roadway while crews work on U.S. 30 eastbou (US 30)until Oct 31
- Lanes closedWestboundU.S. 30 at the east and west bridges over the Norfolk Southern Railroad, just west of SR 98, will be reduced to one lane of traffic in each direction for a bridge replacement project. On Wednesday, May 20 traffic will be switched into a new pattern using the median crossovers. One 11’ lane in each direction will be maintained on the westbound side of the roadway while crews work on U.S. 30 eastbou (US 30)until Oct 31
US-33 42 work zones
- Road closedSouthboundRoad closure for U.S. 33 expansion project (PLEASANTON RD)until Nov 20
- Road closedNorthboundRoad closure for U.S. 33 expansion project (PLEASANTON RD)until Nov 20
- Lanes closedSouthboundThe James Rd. ramp to U.S. 33 eastbound will have various overnight lane restrictions (7 p.m. - 5 a.m.) (RAMP FROM MR 4254N S JAMES RD TO US 33)until Nov 4
- Lanes open, work nearbyEastbound12 ft. width restriction on SR 595 entrance ramp to U.S. 33 east (RAMP FROM SR 595 TO US 33)until Nov 7
- Lanes closedEastboundLane closures for resurfacing (RAMP FROM SR 595 TO US 33)until Nov 7
- Lanes closedEastboundLane closures for resurfacing (RAMP FROM SR 93 MULBERRY ST S TO US 33)until Nov 7
- Lanes open, work nearbyEastbound12 ft width restriction SR 93 on ramp to U.S. 33 East (RAMP FROM SR 93 MULBERRY ST S TO US 33)until Nov 7
- Lanes open, work nearbyEastbound12 ft. width restriction on TR 346 Nelsonville Entrance Ramp to U.S. 33 eastbound (RAMP FROM TR 346 SIMONTON RD TO US 33)until Nov 7
- Lanes open, work nearbyEastbound12 ft. width restriction on TR 346 Nelsonville Exit Ramp from U.S. 33 eastbound (RAMP FROM US 33 TO RA 05040)until Nov 7
- Lanes closedSouthboundLane closures for resurfacing (RAMP FROM US 33 TO SR 328I)until Nov 7
US-35 8 work zones
- Road closedSouthboundAll southbound lanes are being detoured (except for the ramp to westbound U.S. 35). (N BRIDGE ST)until Nov 27
- Road closedSouthboundAll southbound lanes are being detoured (except for the ramp to westbound U.S. 35). (N BRIDGE ST)until Nov 27
- Road closedEastboundTraffic exiting the shopping centers south of U.S. 35 can access U.S. 35 east by going south on Bridge Street to East Main Street and east on Main Street to U.S. 35 (RAMP FROM SR 159 N BRIDGE ST TO US 35)until Nov 30
- Lanes closedEastboundTwo lanes of traffic are maintained on the ramp to northbound SR 159. (RAMP FROM US 35 TO SR 159 N BRIDGE ST)until Nov 27
- Lanes closedEastboundIntermittent lane/shoulder closures for sign replacements (US 35)until Nov 30
- Lanes closedWestboundTree trimming project on U.S. 35 between the Ross County line and Chillicothe Pike. (US 35)until Nov 6
- Lanes closedEastboundTree trimming project on U.S. 35 between the Ross County line and Chillicothe Pike. (US 35)until Nov 6
- Lanes closedWestboundLane closure for bridge deck repair. 17 ft. width restriction in place. (US 35)until Nov 2
US-36 1 work zone
- Lanes closedEastboundU.S. 36 at SR 37 will have various lane restrictions starting Wednesday, October 28 through Sunday, November 15. (E CENTRAL AVE)until Nov 15
US-42 15 work zones
- Lanes closedWestboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (ASHLAND RD)until Dec 31
- Lanes closedEastboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (ASHLAND RD)until Dec 31
- Lanes closedWestboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (ASHLAND RD)until Dec 31
- Lanes closedEastboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (ASHLAND RD)until Dec 31
- Lanes closedWestboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (ASHLAND RD)until Dec 31
- Lanes closedEastboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (ASHLAND RD)until Dec 31
- Lanes closedNorthboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (EASTVIEW DR)until Dec 31
- Lanes closedNorthboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (N STEWART RD)until Dec 31
- Lanes closedSouthboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (N STEWART RD)until Dec 31
- Lanes closedSouthboundU.S. 42 will have traffic signal upgrades at Hanley Road, the Kroger entrance near Stewart Road, Stewart Road, and Reiser Road/Eastview Drive intersections. Traffic will be maintained with shoulder work zones or daytime lane closures when necessary. (REISER DR)until Dec 31
US-50 5 work zones
- Lanes closedNorthboundA resurfacing project on S.R. 128, between U.S. 50 at Cleves and Harrison Avenue. Beginning Thursday, May 14, single-lane closures will be in effect daily, from 8:30 a.m. to 3 p.m. and from 7 p.m. to 6:30 a.m. the following day. Traffic will be maintained by flaggers and/or other traffic control devices during hours of operation. (HAMILTON CLEVES RD)until Nov 2
- Road closedSouthboundOn or after Tuesday, June 30, the ramp from I-75 South to Second Street (Exit 1A) will be closed at 11 p.m. to start demolition. Traffic will be detoured by way of W. 5th Street (Exit 1C) and Race Street to Second Street. This is a permanent closure, and the ramp will be replaced with a new ramp to 3rd Street, with access to 2nd Street. (RAMP FROM US 50 W 6TH ST TO MR 8654 W 2ND ST)until Nov 1
- Road closedEastboundOn or after Sunday, June 28, the ramp from eastbound U.S. 50/W. 6th Street Viaduct to Second Street will be closed for demolition. Motorists will be detoured by way of Freeman Avenue, Mehring Way, and Elm Street to Second Street. This is a permanent closure. (RAMP FROM US 50 W 6TH ST TO MR 8654 W 2ND ST)until Nov 1
- Road closedWestboundThe ramp from westbound U.S. 50/Sixth Street Viaduct to Gest Street will be closed Wednesday, July 15. This will be a permanent closure. Motorists will be detoured by way of Linn Street and the W. 6th Street service road. (RAMP FROM US 50N FT WSHNGTN WB TO W 6TH WB ST RAMP TO MR 1339 GEST ST)until Nov 7
- Lanes closedWestboundBridge painting and repairs on U.S. 50 at the bridge over the Great Miami River, between S.R. 128 and S.R. 264. Westbound U.S. 50 is reduced to one, 10-foot lane; eastbound U.S. 50 should not be affected by this restriction. (US 50)until Nov 30
US-52 7 work zones
- One lane, alternatingNorthboundBridge replacement project on U.S. 52 over Redoak Creek between U.S. 68 and Cherry Street. (CHERRY ST)until Dec 31
- One lane, alternatingWestboundBridge replacement project on U.S. 52 over Redoak Creek between U.S. 68 and Cherry Street. (S 2ND ST)until Dec 31
- One lane, alternatingEastboundBridge replacement project on U.S. 52 over Redoak Creek between U.S. 68 and Cherry Street. (S 2ND ST)until Dec 31
- Lanes closedWestboundA joint repair project on U.S. 52, between the I-275 interchange in Hamilton County and Beckjord Road in Clermont County. Traffic will be maintained in a minimum of one, 11-foot lane in either direction. (US 52)until Nov 21
- Lanes closedEastboundA joint repair project on U.S. 52, between the I-275 interchange in Hamilton County and Beckjord Road in Clermont County. Traffic will be maintained in a minimum of one, 11-foot lane in either direction. (US 52)until Nov 21
- Lanes closedWestboundA joint repair project on U.S. 52, between the I-275 interchange in Hamilton County and Beckjord Road in Clermont County. Traffic will be maintained in a minimum of one, 11-foot lane in either direction. (US 52)until Nov 21
- Lanes closedEastboundA joint repair project on U.S. 52, between the I-275 interchange in Hamilton County and Beckjord Road in Clermont County. Traffic will be maintained in a minimum of one, 11-foot lane in either direction. (US 52)until Nov 21
US-62 2 work zones
- Lanes closedSouthboundResurfacing on U.S. 62, between the Highland County line and the junction with Highland Avenue, Clinton Avenue and Court Street in Washington Court House. Traffic will be maintained in one lane with the use of flaggers. (LEESBURG AVE)until Sep 18
- Lanes closedNorthboundResurfacing on U.S. 62, between the Highland County line and the junction with Highland Avenue, Clinton Avenue and Court Street in Washington Court House. Traffic will be maintained in one lane with the use of flaggers. (US 62)until Sep 18
US-68 3 work zones
- Lanes closedNorthboundUS 68 between SR 55/Lewis B Moore Drive and Springfield Pike will be subject to lane restrictions from 7 a.m. to 5 p.m. starting Tuesday, August 18 through fall 2026. Traffic will be maintained by a flagging operation when necessary. Crews will be repairing the bridge. (SPRINGFIELD URBANA PIKE)until Nov 6
- Lanes closedNorthboundUS 68 between SR 55/Lewis B Moore Drive and Springfield Pike will be subject to lane restrictions from 7 a.m. to 5 p.m. starting Tuesday, August 18 through fall 2026. Traffic will be maintained by a flagging operation when necessary. Crews will be repairing the bridge.until Nov 6
- Lanes open, work nearbyNorthboundConstruction of safe pedestrian and bicycle connections b/t the Little Miami Scenic Trail and the new Shawnee Interceptive Education Center. (US68)until Jun 1
US-127 4 work zones
- Lanes closedEastboundA resurfacing project on S.R. 73, between U.S. 127 at Seven Mile and the western corporation limit of Trenton. Work will begin Monday, April 20, with pavement repairs, and resurfacing will begin in mid to late May. Traffic will be maintained in one lane with the use of flaggers. (TRENTON OXFORD RD)until Nov 1
- Lanes closedNorthboundUS 127 between Seigrist Jutte Road and Sebastian Road will intermittently be reduced to a single lane from 7 a.m. to 7 p.m. through fall 2026. Traffic will be maintained by a flagging operation. Crews will be repairing and resurfacing the roadway.until Nov 16
- Lanes closedSouthboundUS 127 between Seigrist Jutte Road and Sebastian Road will intermittently be reduced to a single lane from 7 a.m. to 7 p.m. through fall 2026. Traffic will be maintained by a flagging operation. Crews will be repairing and resurfacing the roadway.until Nov 16
- Lanes closedNorthboundA pavement repair and resurfacing project on S.R. 503, between U.S. 127 at Seven Mile and the Preble County line. Traffic will be maintained in a minimum of one, 11-foot lane with the use of flaggers and/or traffic control devices. (WEST ELKTON RD)until Nov 1
US-224 3 work zones
- Road closedEastboundSR 224 will be closed for 120 days due to bridge rehabilitation. (US 224)until Nov 24
- Lanes closedWestboundBeginning Thursday morning, June 4, I-277/U.S. 224 over I-77 will be reduced to one lane in each direction for bridge repairs. (US 224)until Nov 13
- Road closedWestboundSR 224 will be closed for 120 days due to bridge rehabilitation. (US 224)until Nov 24
State highways
SR-2 2 work zones
- Lanes closedEastboundSR 2 from just west of the SR 4 (Hayes Ave) interchange to just east of Rye Beach Road will have single lane closures for a resurfacing project.until Sep 30
- Lanes closedWestboundSR 2 from just west of the SR 4 (Hayes Ave) interchange to just east of Rye Beach Road will have single lane closures for a resurfacing project.until Sep 30
SR-3 2 work zones
- Lanes closedSouthboundSR 3 from the city of Wooster corporation limits to just south of SR 226 will have single lane closures for pavement repairs and resurfacing. One lane of traffic will be maintained in each direction at all times. (S COLUMBUS RD)until Nov 30
- Lanes closedNorthboundSR 3 from the city of Wooster corporation limits to just south of SR 226 will have single lane closures for pavement repairs and resurfacing. One lane of traffic will be maintained in each direction at all times. (S COLUMBUS RD)until Nov 30
SR-4 8 work zones
- Lanes closedNorthboundResurfacing on S.R. 4 (Springfield Pike), between Barron Drive and Sharon Road. Construction also includes paving S.R. 747 (Congress Avenue), from its junction with S.R. 4 to just north of Coral Avenue. Traffic will be maintained in a minimum of one lane in each direction. (CONGRESS AVE)until Nov 7
- Lanes closedSouthboundResurfacing on S.R. 4 (Springfield Pike), between Barron Drive and Sharon Road. Construction also includes paving S.R. 747 (Congress Avenue), from its junction with S.R. 4 to just north of Coral Avenue. Traffic will be maintained in a minimum of one lane in each direction. (CONGRESS AVE)until Nov 7
- Road closedNorthboundThe ramp from US 35 East and West to I-75 North will be closed overnight from 10 p.m. to 5 a.m. starting Sunday, November 1 through early Monday, November 2. Crews will be repairing the concrete wall along the ramp. (RAMP FROM US 35N TO SR 4)from Sun, Nov 1, 10:00 PM, until Nov 2
- Lanes closedNorthboundResurfacing on S.R. 4 (Springfield Pike), between Barron Drive and Sharon Road. Construction also includes paving S.R. 747 (Congress Avenue), from its junction with S.R. 4 to just north of Coral Avenue. Traffic will be maintained in a minimum of one lane in each direction. (SPRINGFIELD PIKE)until Nov 7
- Lanes closedSouthboundResurfacing on S.R. 4 (Springfield Pike), between Barron Drive and Sharon Road. Construction also includes paving S.R. 747 (Congress Avenue), from its junction with S.R. 4 to just north of Coral Avenue. Traffic will be maintained in a minimum of one lane in each direction. (SPRINGFIELD PIKE)until Nov 7
- Lanes closedNorthboundSR 4 from Bogart Road to Perkins Ave. will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers.until Sep 30
- Lanes closedSouthboundSR 4 from Bogart Road to Perkins Ave. will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers.until Sep 30
- Road closedNorthboundThe ramp from US 35 East and West to I-75 North will be closed overnight from 10 p.m. to 5 a.m. starting Sunday, November 1 through early Monday, November 2. Crews will be repairing the concrete wall along the ramp. (SR 4)from Sun, Nov 1, 10:00 PM, until Nov 2
SR-7 11 work zones
- Road closedNorthboundThe ramp is closed due to a slope failure at this location. Construction is estimated to begin in the spring of 2026 and be completed in the fall of 2026. (RAMP FROM MR 173 COMMERCIAL ST TO SR 7)until Oct 31
- Road closedSouthboundThe southbound ramp for SR 7 at this location is closed for work relating to a slide repair project near this location. The detour for the ramp is to take Old State Route 7 north to SR 152, then turn south onto SR 7. (RAMP FROM SR 7I ALEXANDER ST TO SR 7N)until Nov 14
- Lanes closedSouthboundIntermittent lane and shoulder closures in each direction with drums for sign replacements (SR 7)until Nov 30
- Lanes closedNorthboundIntermittent lane and shoulder closures in each direction with drums for sign replacements (SR 7)until Nov 30
- Lanes closedSouthboundOne lane of traffic is maintained throughout construction. The completion date is October 31, 2026. (SR 7)until Nov 30
- Lanes closedSouthboundTemporary traffic signals in place for bridge deck replacement (SR 7)until Nov 1
- Lanes closedNorthboundSlide repair along the northbound lanes of State Route 7 located just south of the 4th Street EXIT ramp in Toronto. One lane of traffic is maintained. (SR 7)until Nov 14
- Lanes closedNorthboundSlide repair along the northbound lanes of State Route 7 located just south of the 4th Street EXIT ramp in Toronto. One lane of traffic is maintained. (SR 7)until Nov 14
- Lanes closedEastboundExpect daily lane closures on eastbound SR 7 between the U.S. 52 interchange and the SR 527 interchange.until Nov 13
- Lanes closedNorthboundIntermittent lane and shoulder closures in each direction with drums for sign replacements (SR 7)until Nov 30
SR-8 2 work zones
- Road closedNorthbound• Perkins St. to SR 8 north. The detour will be Perkins St. to Goodkirk St. to Buchtel Ave. to Fountain St. to SR 8 northbound. • SR 8 northbound to Glenwood Ave. The detour will be Tallmadge Ave to Home Ave. • SR 8 south to Buchel Ave. The detour will be SR 8 south to Perkins St. to Goodkirk St. (PERKINS ST TO SR 8 N)until Aug 1
- Lanes open, work nearbyNorthboundAll three lanes of SR 8 northbound sand southbound are moved onto the new SR 8 southbound bridge.until Aug 1
SR-10 1 work zone
- Lanes closedEastboundSR 10 (Lorain Rd.) between Sterns Rd. and Dover Center Rd. will be reduced to two lanes in each direction beginning Monday, October 19, through November. (LORAIN RD)until Nov 13
SR-11 1 work zone
- Road closedNorthboundThe SR 11 northbound ramp and the U.S. 30 westbound ramp are closed at this location for construction. Additionally, U.S. 30 westbound under SR 11 is closed. (RAMP FROM CR 425 EAST LIVERPOOL RD TO SR 11)until Nov 13
SR-13 4 work zones
- One lane, alternatingSouthboundSR 13 from the Knox County line through the village of Bellville to Andrews Road will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers.until Nov 7
- One lane, alternatingNorthboundSR 13 from the Knox County line through the village of Bellville to Andrews Road will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers.until Nov 7
- Lanes closedNorthboundSR 13 northbound and southbound, from Hanley Road to Chilton Ave, will have closures for a resurfacing project. Traffic will be maintained in a 12-ft lane using barrels. (SR-13)until May 30
- Lanes closedSouthboundSR 13 northbound and southbound, from Hanley Road to Chilton Ave, will have closures for a resurfacing project. Traffic will be maintained in a 12-ft lane using barrels. (SR-13)until May 30
SR-16 2 work zones
- Lanes open, work nearbyEastboundRehabilitation and replacement of composite pavement on State Route 16 and State Route 37 in Licking County. Overnight lane and intermittent ramp closures are in place. Please follow all posted detours. (SR 16)until Oct 15
- Lanes open, work nearbyWestboundRehabilitation and replacement of composite pavement on State Route 16 and State Route 37 in Licking County. Overnight lane and intermittent ramp closures are in place. Please follow all posted detours. (SR 16)until Oct 15
SR-17 2 work zones
- Road closedEastboundDetour: • Eastbound traffic will be detoured via Clague Rd. to I-480 east to the SR 17/SR 237 exit. • Westbound traffic will be detoured via Grayton Rd. to I-480 west to Clague Rd. to Brookpark Rd. (BROOKPARK RD)until Sep 3
- Road closedWestboundDetour: • Eastbound traffic will be detoured via Clague Rd. to I-480 east to the SR 17/SR 237 exit. • Westbound traffic will be detoured via Grayton Rd. to I-480 west to Clague Rd. to Brookpark Rd. (BROOKPARK RD)until Sep 3
SR-19 2 work zones
- One lane, alternatingNorthboundSR 19 from the city of Bucyrus to the city of Galion corporation limits will have single lane closures for pavement repairs and resurfacing. Traffic will be maintained by flaggers.until Nov 30
- One lane, alternatingSouthboundSR 19 from the city of Bucyrus to the city of Galion corporation limits will have single lane closures for pavement repairs and resurfacing. Traffic will be maintained by flaggers.until Nov 30
SR-26 1 work zone
- One lane, alternatingSouthboundLane closure with temporary traffic signals for AEP structure maintenance on SR 26 (SR26)until Nov 30
SR-28 2 work zones
- Lanes closedEastboundA chip-seal paving project on S.R. 28, from just west of High Street/Gibson Road at Martinsville to S.R. 73 at New Vienna. Construction will begin on or after June 1, and throughout the project, traffic will be maintained with the use of flaggers and/or other traffic control devices. (WEST ST)until Nov 1
- Lanes closedWestboundA bridge repair project on S.R. 28, between S.R. 73 and Phillips Road in New Vienna. Throughout most construction, traffic will be maintained in one lane with the use of flaggers. (WEST ST)until Nov 1
SR-32 6 work zones
- Lanes closedEastboundResurfacing project on SR 32 between the Brown County line and village of Seaman corporation limit. (APPALACHIAN HWY)until Nov 13
- Lanes closedWestboundResurfacing project on SR 32 between the Brown County line and village of Seaman corporation limit. (APPALACHIAN HWY)until Nov 13
- Lanes closedWestboundIntersection improvement project to increase safety at the intersection of SR 32, SR 124, and Tennyson Road.until Nov 13
- Lanes closedEastboundIntersection improvement project to increase safety at the intersection of SR 32, SR 124, and Tennyson Road.until Nov 13
- Lanes closedWestboundExpect daily lane closures from 7:00 a.m. to 5:00 p.m. on SR 32 between Laurel Ridge Road and Dover Road.until Nov 30
- Lanes closedEastboundExpect daily lane closures from 7:00 a.m. to 5:00 p.m. on SR 32 between Laurel Ridge Road and Dover Road.until Nov 30
SR-37 3 work zones
- Road closedNorthboundSR 37 over the Scioto River in the Village of La Rue will close starting Monday, June 22 for 120 days (S HIGH ST)until Dec 31
- Lanes closedWestboundRehabilitation and replacement of composite pavement on State Route 16 and State Route 37 in Licking County. Overnight lane and intermittent ramp closures are in place. Please follow all posted detours. (SR 37)until Oct 15
- Lanes closedEastboundRehabilitation and replacement of composite pavement on State Route 16 and State Route 37 in Licking County. Overnight lane and intermittent ramp closures are in place. Please follow all posted detours. (SR 37)until Oct 15
SR-44 6 work zones
- One lane, alternatingNorthboundSR 44 between Mentor Rd. and Girdled Rd. will have various lane restriction through November. (CENTER ST)until Nov 20
- Road closedSouthboundSR 44 under SR 283 will be reduced to one lane in each direction through November.until Nov 20
- One lane, alternatingNorthboundSR 44 between Mentor Rd. and Girdled Rd. will have various lane restriction through November.until Nov 20
- One lane, alternatingSouthboundSR 44 between Mentor Rd. and Girdled Rd. will have various lane restriction through November.until Nov 20
- One lane, alternatingSouthboundSR 44 between Mentor Rd. and Girdled Rd. will have various lane restriction through November.until Nov 20
- Road closedNorthboundSR 44 under SR 283 will be reduced to one lane in each direction through November.until Nov 20
SR-46 3 work zones
- One lane, alternatingEastbound• Traffic on SR 46 southbound will not be able to turn onto East Market Street eastbound. The detour will be SR 46 south to SR 82 east to Howland Wilson Rd. to East Market St. • Traffic on SR 46 northbound will not be able to turn onto East Market Street westbound. The detour will be SR 82 east to Howland Wilson Rd. to E. Market St (EAST MARKET ST)until Dec 31
- One lane, alternatingNorthbound• Traffic on SR 46 southbound will not be able to turn onto East Market Street eastbound. The detour will be SR 46 south to SR 82 east to Howland Wilson Rd. to East Market St. • Traffic on SR 46 northbound will not be able to turn onto East Market Street westbound. The detour will be SR 82 east to Howland Wilson Rd. to E. Market St (NILES CORTLAND RD)until Dec 31
- Lanes closedNorthboundSR 46 between Morris St. and Seaborn St. has various lane restrictions for sidewalk installation. Estimated completion, mid-December 2026.until Dec 18
SR-57 1 work zone
- Lanes closedWestboundA resurfacing project in the city of Elyria along U.S. 20 (John F. Kennedy Memorial Parkway), from Chestnut Ridge Road to Cleveland Street, and along SR 301 (Abbe Road), from Kennedy Memorial Parkway to just north of Antioch Drive. Traffic will be maintained at all times. Night work will conitnue on U.S. 20 from Chestnut Ridge Road to Cleveland Street. (NB SR 57)until Nov 30
SR-60 3 work zones
- One lane, alternatingNorthboundTemporary traffic signals in place for landslide repair (SR 60)until Dec 31
- One lane, alternatingSouthboundTemporary traffic signals in place for landslide repair (SR 60)until Dec 31
- One lane, alternatingNorthboundTraffic maintained with temporary signals for culvert replacement (SR 60)until Nov 25
SR-66 1 work zone
- Road closedSouthboundSR 66 between SR 47 and Rangeline Road will be closed starting Tuesday, October 13 through Monday, November 2. Crews will be replacing a culvert.until Nov 2
SR-73 7 work zones
- Lanes closedEastboundResurfacing on S.R. 73, from the intersection with 1st Street in the city of Trenton to Radabaugh Road. Traffic will be maintained in one lane with the use of flaggers. (E STATE ST)until Nov 1
- Lanes closedWestboundResurfacing on S.R. 73, from the intersection with 1st Street in the city of Trenton to Radabaugh Road. Traffic will be maintained in one lane with the use of flaggers. (OXFORD STATE RD)until Nov 1
- Lanes closedWestboundResurfacing on S.R. 73, between its junction with S.R. 741 in the city of Springboro to Red Lion Five Points Road. Traffic will be maintained in a minimum of one lane in either direction with the use of flaggers and traffic control devices. (SR 73)until Nov 1
- One lane, alternatingNorthboundBridge replacement project on SR 73 between Line Road and Mad River Road.until Nov 30
- One lane, alternatingSouthboundBridge replacement project on SR 73 between Line Road and Mad River Road.until Nov 30
- Lanes closedEastboundResurfacing S.R. 73, between Red Lion- Five Points Road and Harveysburg Road, as well as the installation of a left-turn lane on S.R. 73 at Old S.R. 73 near Waynesville. Traffic will be maintained in one lane in either direction with the use of flaggers and/or other traffic control devices. (SR 73)until Nov 30
- Lanes closedEastboundResurfacing on S.R. 73, between its junction with S.R. 741 in the city of Springboro to Red Lion Five Points Road. Traffic will be maintained in a minimum of one lane in either direction with the use of flaggers and traffic control devices. (W CENTRAL AVE)until Nov 1
SR-84 1 work zone
- One lane, alternatingEastboundSR 84 between SR 91 and the Cuyahoga County line will have various lane restrictions through November. (S WOODLAND RD)until Nov 30
SR-86 1 work zone
- Road closedWestboundBeginning Monday, October 19, SR 86 just east of Ireland Rd. will be closed through early November for a culvert replacement. The detour will be SR 86 to SR 528 to US 322 to SR 534.until Nov 9
SR-87 1 work zone
- One lane, alternatingWestboundSR 84 between SR 91 and the Cuyahoga County line will have various lane restrictions through November. (SR 87)until Nov 30
SR-93 6 work zones
- Lanes open, work nearbyWestbound12 foot width restriction SR 93 On Ramp to US 33 west (RAMP FROM SR 93 MULBERRY ST S TO US 33N)until Nov 7
- Lanes closedWestboundLane closures for resurfacing (RAMP FROM SR 93 MULBERRY ST S TO US 33N)until Nov 7
- Lanes open, work nearbyWestbound12 ft width restriction on SR 93 Off Ramp from US 33 west (RAMP FROM US 33N TO SR 93 MULBERRY ST S)until Nov 7
- Lanes closedWestboundLane closures for resurfacing (RAMP FROM US 33N TO SR 93 MULBERRY ST S)until Nov 7
- One lane, alternatingNorthboundState Route 93 will experience daytime lane closures between U.S. Route 36 and the Holmes County line for paving operations. Both directions of travel will be maintained. (SR 93)until Sep 1
- One lane, alternatingNorthboundState Route 93 will experience daytime lane closures between U.S. Route 36 and the Holmes County line for paving operations. Both directions of travel will be maintained. (SR 93)until Sep 1
SR-94 2 work zones
- Road closedSouthboundThe SR 94/585/604 intersection, north of SR 57, will close Monday, July 20 for an intersection improvement project. The current two-way stop-controlled intersection will be converted into a single lane roundabout.until Nov 13
- Road closedNorthboundThe SR 94/585/604 intersection, north of SR 57, will close Monday, July 20 for an intersection improvement project. The current two-way stop-controlled intersection will be converted into a single lane roundabout.until Nov 13
SR-95 6 work zones
- Lanes closedSouthboundSR 95 at James Way will have various lane restrictions starting Monday, May 11 through Fall 2026. (JAMES WAY)until Nov 20
- Lanes closedNorthboundSR 95 at James Way will have various lane restrictions starting Monday, May 11 through Fall 2026. (JAMES WAY)until Nov 20
- Lanes closedWestboundSR 95 at James Way will have various lane restrictions starting Monday, May 11 through Fall 2026. (MARION-MT GILEAD RD)until Nov 20
- Lanes closedEastboundSR 95 at James Way will have various lane restrictions starting Monday, May 11 through Fall 2026. (MARION-MT GILEAD RD)until Nov 20
- One lane, alternatingEastboundSR 95 in the village of Butler, from Simmons Street to Traxler Street, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers.until Nov 7
- One lane, alternatingWestboundSR 95 in the village of Butler, from Simmons Street to Traxler Street, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers.until Nov 7
SR-97 2 work zones
- One lane, alternatingEastboundSR 97 from the village of Bellville through the village of Butler will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers. (MILL)until Nov 7
- One lane, alternatingWestboundSR 97 from the village of Bellville through the village of Butler will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers. (MILL ST)until Nov 7
SR-104 2 work zones
- Lanes open, work nearbyWestboundShoulder closures on SR 104 westbound over Scioto River (FRANK RD)until Dec 31
- Lanes closedSouthboundExpect daily lane closures (8:00 a.m. - 3:00 p.m.) on SR 104 between North Walnut Street and Moundsville Road.until Nov 6
SR-108 1 work zone
- Road closedWestboundState Route 108/Scott St. on-ramp to westbound U.S. Route 24 will close for reconstruction beginning Thursday, October 1 through mid-to-late May 2027. Detour using Scott St./SR 108 to eastbound U.S. 24 to Industrial Dr. to westbound U.S. 24. (RAMP FROM SR 108 N SCOTT ST TO US 6N)until May 17
SR-122 3 work zones
- Lanes closedEastboundAs part of a resurfacing and bridge repair project, S.R. 122 is reduced to one lane at the bridge over Elk Creek, near Hursh Road. Traffic will be maintained with temporary traffic signals. (MIDDLETOWN EATON RD)until Nov 15
- Lanes closedWestboundA resurfacing and bridge repair project on S.R. 122, between the Preble County line and the Great Miami River at Middletown. Traffic will be maintained in one lane by flaggers during daytime hours. (MIDDLETOWN EATON RD)until Nov 21
- Lanes closedEastboundA resurfacing and bridge repair project on S.R. 122, between the Preble County line and the Great Miami River at Middletown. Traffic will be maintained in one lane by flaggers during daytime hours. (MIDDLETOWN EATON RD)until Nov 21
SR-123 1 work zone
- Lanes closedNorthboundA paving/chip-seal project on S.R. 123, between Mason-Morrow-Millgrove Road and S.R. 350. Traffic will be maintained in one,12-foot lane during daytime, working hours, daily from approximately 7 a.m. to 5 p.m. with the use of flaggers and/or traffic control devices. (SR 123)until Nov 6
SR-124 2 work zones
- Lanes closedEastboundIntermittent lane and shoulder closures in each direction with drums for sign replacements (SR 124)until Nov 30
- Lanes closedWestboundIntermittent lane and shoulder closures in each direction with drums for sign replacements (SR 124)until Nov 30
SR-125 2 work zones
- Lanes closedEastboundA resurfacing project on S.R. 125, between S.R. 222 North and Kelli Lane at Bethel. Traffic will be maintained in a minimum of one lane in either direction, during hours of operation, daily from approximately 7 a.m. to 8 p.m. (SR 125)until Nov 15
- Lanes closedWestboundA resurfacing project on S.R. 125, between S.R. 222 North and Kelli Lane at Bethel. Traffic will be maintained in a minimum of one lane in either direction, during hours of operation, daily from approximately 7 a.m. to 8 p.m. (W PLANE ST)until Nov 15
SR-126 3 work zones
- Lanes closedEastboundA resurfacing project on S.R. 126/Cross County Highway, between Colerain Avenue and W. Galbraith Road. Traffic will be maintained in a minimum of one lane in either direction. Various ramp closures may be in effect during evening and overnight hours. (RONALD REAGAN CROSS CO EB HWY)until Nov 2
- Lanes closedEastboundA resurfacing project on S.R. 126/Cross County Highway, between Colerain Avenue and W. Galbraith Road. Traffic will be maintained in a minimum of one lane in either direction. Various ramp closures may be in effect during evening and overnight hours. (RONALD REAGAN CROSS CO EB HWY)until Nov 2
- Lanes closedWestboundA resurfacing project on S.R. 126/Cross County Highway, between Colerain Avenue and W. Galbraith Road. Traffic will be maintained in a minimum of one lane in either direction. Various ramp closures may be in effect during evening and overnight hours. (RONALD REAGAN CROSS CO WB HWY)until Nov 2
SR-131 2 work zones
- Lanes open, work nearbyEastboundBridge replacement project on SR 131 between Marathon Edenton Road and Woodward Road.until Nov 13
- Lanes open, work nearbyWestboundBridge replacement project on SR 131 between Marathon Edenton Road and Woodward Road.until Nov 13
SR-134 1 work zone
- Road closedNorthboundA bridge replacement project on S.R. 134 over the East Fork Little Miami River, just north of the junction with S.R. 124. Beginning July 20, S.R. 134 will be closed for up to 120 days, and motorists will be detoured by way of U.S. 50, U.S. 68 and S.R. 28. (SR 134)until Nov 30
SR-136 2 work zones
- One lane, alternatingWestboundResurfacing project on SR 136 from the Adams County line to U.S. 62.until Nov 6
- One lane, alternatingEastboundResurfacing project on SR 136 from the Adams County line to U.S. 62.until Nov 6
SR-159 4 work zones
- Lanes closedSouthboundExpect lane closures on SR 159 (Bridge Street) between Pawnee Road and North Plaza Blvd. (N BRIDGE ST)until Nov 27
- Road closedWestboundNB Bridge Street to U.S. 35 W ramp is currently closed. Traffic must use the temporary ramp from the left lane to access US 35 west. (RAMP FROM SR 159 N BRIDGE ST TO US 35N)until Nov 30
- Lanes closedSouthboundProject will construct truck parking facilities at the U.S. 23 and SR 159 interchange.until Nov 27
- Lanes closedNorthboundProject will construct truck parking facilities at the U.S. 23 and SR 159 interchange.until Nov 27
SR-164 2 work zones
- Lanes open, work nearbyNorthboundOne lane of traffic is maintained with flaggers. The completion date is September 30, 2026. (SR 164)until Nov 30
- Lanes open, work nearbyNorthboundOne lane of traffic is maintained with flaggers. The completion date is September 30, 2026. (SR 164)until Nov 30
SR-179 2 work zones
- Road closedNorthbound120 day closure for a bridge rehabilitation project. Traffic will detour via SR 39 west to SR 3 north, and reverse. (SR 179)until Dec 23
- Road closedSouthbound120 day closure for a bridge rehabilitation project. Traffic will detour via SR 39 west to SR 3 north, and reverse. (SR 179)until Dec 23
SR-199 4 work zones
- Road closedSouthboundSR 199 will be closed for 2 months due to a sewer project. (N WARPOLE ST)until Nov 20
- Road closedNorthboundSR 199 will be closed for 2 months due to a sewer project. (N WARPOLE ST)until Nov 20
- Road closedEastboundthe SR199 bridge over US23 will be closed for a bridge overlay (SR 199)until Nov 25
- Road closedWestboundthe SR199 bridge over US23 will be closed for a bridge overlay (SR 199)until Nov 25
SR-213 1 work zone
- One lane, alternatingNorthboundResurfacing work, one lane of traffic will be maintained with flaggers. (SR 213)until Nov 30
SR-229 1 work zone
- Road closedEastboundSR 229 east of Weiser Rd. will close starting Monday, October 19 for 30 days.until Nov 17
SR-241 2 work zones
- Road closedNorthboundBeginning on Friday, October 16, SR 241 between Shuffel St. and Willowdale Lake Ave. will be closed through fall 2027 for a bridge replacement and pavement reconstruction. The truck detour will be SR 241 to I-77 to SR 687. The local detour will be Shuffel Rd. to Frank Ave. to Strausser St. (WALES AVE)until Sep 30
- Road closedSouthboundBeginning on Friday, October 16, SR 241 between Shuffel St. and Willowdale Lake Ave. will be closed through fall 2027 for a bridge replacement and pavement reconstruction. The truck detour will be SR 241 to I-77 to SR 687. The local detour will be Shuffel Rd. to Frank Ave. to Strausser St. (WALES AVE)until Sep 30
SR-243 2 work zones
- Road closedNorthboundChesapeake Bypass Phase 2 Project. Beginning April 6, SR 243 will be permanently closed between CR 118 (Bent Creek Road) and CR 32 (Eaton Road).until Nov 15
- Road closedSouthboundChesapeake Bypass Phase 2 Project. Beginning April 6, SR 243 will be permanently closed between CR 118 (Bent Creek Road) and CR 32 (Eaton Road).until Nov 15
SR-245 2 work zones
- Road closedEastboundThe Northwest Parkway / 5th Street ramp to U.S 33 eastbound will be closed starting Friday, August 31 for 90 days. (RAMP FROM US 33IN NORTHWEST PKWY TO SR 245)until Nov 21
- Road closedEastboundThe Northwest Parkway / 5th Street ramp to U.S 33 eastbound will be closed starting Friday, August 31 for 90 days. (SR 245)until Nov 21
SR-283 2 work zones
- Lanes closedEastboundSR 283 over SR 44 will be reduced to one lane in each direction through November. (LAKE SHORE BLVD)until Nov 27
- Lanes closedWestboundSR 283 over SR 44 will be reduced to one lane in each direction through November. (LAKE SHORE BLVD)until Nov 27
SR-325 1 work zone
- Lanes closedNorthboundTraffic maintained with temporary signals for culvert repair (SR 325)until Jan 1
SR-328 5 work zones
- Lanes closedSouthboundLane closures for resurfacing (SR 328)until Nov 7
- Lanes closedNorthboundLane closures for resurfacing (SR 328)until Nov 7
- Lanes open, work nearbyEastbound12 ft width restriction SR 328 On Ramp to US 33 eastbounduntil Nov 7
- Lanes closedSouthboundLane closures for resurfacing (SR 328)until Nov 7
- Lanes closedNorthboundLane closures for resurfacing (SR 328)until Nov 7
SR-345 1 work zone
- One lane, alternatingWestboundMotorists can expect flagged lane closures on SR 669 for chip seal. (SR 345)until Nov 13
SR-350 1 work zone
- Lanes closedEastboundA resurfacing project on S.R. 350, between 1st Street in Clarksville and the intersection with S.R. 730. Throughout the project, traffic will be maintained in one lane with the use of flaggers and/or traffic control devices. (CUBA AVE)until Nov 1
SR-374 4 work zones
- Lanes closedNorthboundTemporary traffic signals in place for guardrail work (SR 374)until Nov 30
- Lanes closedSouthboundTemporary traffic signals in place for guardrail work (SR 374)until Nov 30
- Lanes closedNorthboundTemporary traffic signals in place for guardrail work (SR 374)until Nov 30
- Lanes closedSouthboundTemporary traffic signals in place for guardrail work (SR 374)until Nov 30
SR-412 1 work zone
- Lanes closedEastboundEastbound U.S. Route 20 east of SR 412 will be reduced to one lane during construction. (RT 20 BYPASS)until Dec 1
SR-510 3 work zones
- One lane, alternatingNorthboundState Route 510, between Clyde and Buck Creek, will experience lane restrictions for resurfacing through November. (N MAIN ST)until Nov 30
- One lane, alternatingSouthboundState Route 510, between Clyde and the Ohio Turnpike, will be reduced to one lane for resurfacing through early November. Traffic maintained by temporary traffic signals with traffic alternating one way. (N SR 510)until Nov 7
- Road closedSouthboundState Route 510, between State Route 412 and U.S. Route 6, will be closed for full-depth pavement reconstruction beginning Monday, August 10. Local residential and business access will be maintained by flaggers for northbound when approaching from SR 412. No southbound traffic will be permitted from US 6. Commercial detour: SR 412 to US 20 to US 6 and vise versa. (N SR 510)until Dec 1
SR-511 2 work zones
- One lane, alternatingNorthboundSR 511 from Township Road 462 to the Lorain County Line will be reduced to one lane of traffic for a resurfacing project. Traffic will be maintained by flaggers.until Nov 13
- One lane, alternatingSouthboundSR 511 from Township Road 462 to the Lorain County Line will be reduced to one lane of traffic for a resurfacing project. Traffic will be maintained by flaggers.until Nov 13
SR-520 2 work zones
- Road closedEastboundOctober 26-November 6, U.S. 62 will be closed for culvert replacement. (SR 520)until Nov 6
- Road closedWestboundOctober 26-November 6, U.S. 62 will be closed for culvert replacement. (SR 520)until Nov 6
SR-521 2 work zones
- One lane, alternatingEastboundSR 521 over Alum Creek is reduced to one lane. Two-way traffic is being maintained using a temporary traffic signal.until Nov 12
- One lane, alternatingWestboundSR 521 over Alum Creek is reduced to one lane. Two-way traffic is being maintained using a temporary traffic signal.until Nov 12
SR-555 6 work zones
- Road closedNorthboundState Route 555 will close to traffic between Pletcher Hill Road and Bush Hill Road for slope repair. (CENTER RD)until Nov 1
- Road closedSouthboundState Route 555 will close to traffic between Pletcher Hill Road and Bush Hill Road for slope repair. (CENTER RD)until Nov 1
- One lane, alternatingSouthboundTemporary traffic signals/10 ft. width restriction in place for bridge replacement (SR 555)until Nov 6
- One lane, alternatingNorthboundTemporary traffic signals/10 ft. width restriction in place for bridge replacement (SR 555)until Nov 6
- One lane, alternatingSouthboundTemporary traffic signals/10 ft. width restriction in place for bridge replacement (SR 555)until Nov 6
- One lane, alternatingNorthboundTemporary traffic signals/10 ft. width restriction in place for bridge replacement (SR 555)until Nov 6
SR-562 1 work zone
- Lanes closedWestboundReplacement of three railroad bridges located over Prosser Avenue, I-75, and SR 562 and minor realignment of I-75 lanes to accommodate railroad bridge piers. Various lane closures will be in effect on I-75, as well as on S.R. 562, as work progresses on the structures over these routes. (SR562 RAMP)until Jun 30
SR-585 6 work zones
- One lane, alternatingSouthboundSR 585 from the city of Wooster corporation limits to Smithville Western Road will have single lane closures for pavement repairs and resurfacing. Traffic will be maintained by flaggers.until Nov 30
- One lane, alternatingNorthboundSR 585 from the city of Wooster corporation limits to Smithville Western Road will have single lane closures for pavement repairs and resurfacing. Traffic will be maintained by flaggers.until Nov 30
- Road closedNorthboundSR 585 between Steiner Road and Warwick Road is closed for an emergency culvert replacement.until Nov 6
- Road closedNorthboundThe SR 94/585/604 intersection, north of SR 57, will close Monday, July 20 for an intersection improvement project. The current two-way stop-controlled intersection will be converted into a single lane roundabout. (SR 585)until Nov 13
- Road closedSouthboundSR 585 between Steiner Road and Warwick Road is closed for an emergency culvert replacement.until Nov 6
- Road closedSouthboundThe SR 94/585/604 intersection, north of SR 57, will close Monday, July 20 for an intersection improvement project. The current two-way stop-controlled intersection will be converted into a single lane roundabout. (SR 585)until Nov 13
SR-595 3 work zones
- Lanes open, work nearbyEastbound12 ft width restriction on SR 595 Exit Ramp from US 33 east for pavement workuntil Nov 7
- Lanes closedSouthboundLane closures for resurfacing (SR 595)until Nov 7
- Lanes closedNorthboundLane closures for resurfacing (SR 595)until Nov 7
SR-604 2 work zones
- Road closedEastboundThe SR 94/585/604 intersection, north of SR 57, will close Monday, July 20 for an intersection improvement project. The current two-way stop-controlled intersection will be converted into a single lane roundabout. (SR 604)until Nov 13
- Road closedWestboundThe SR 94/585/604 intersection, north of SR 57, will close Monday, July 20 for an intersection improvement project. The current two-way stop-controlled intersection will be converted into a single lane roundabout. (SR 604)until Nov 13
SR-613 2 work zones
- Road closedEastboundSR613 will be closed in Melrose for railroad repair (STATE ST)until Nov 2
- Road closedWestboundSR613 will be closed in Melrose for railroad repair (STATE ST)until Nov 2
SR-644 1 work zone
- One lane, alternatingNorthboundDuring construction, traffic will be maintained with temporary traffic signals with a 10-foot width restriction. (SR 644)until Nov 30
SR-650 2 work zones
- Lanes closedSouthboundBridge replacement project on SR 650 between Little Pine Creek Road and Kellys Mill Road.until May 28
- Lanes closedNorthboundBridge replacement project on SR 650 between Little Pine Creek Road and Kellys Mill Road.until May 28
SR-651 1 work zone
- One lane, alternatingWestboundState Route 93 will experience daytime lane closures between U.S. Route 36 and the Holmes County line for paving operations. Both directions of travel will be maintained. (SR 651)until Sep 1
SR-669 3 work zones
- One lane, alternatingWestboundMotorists can expect flagged lane closures on SR 669 for chip seal. (RIDGE AVE)until Nov 13
- One lane, alternatingEastboundMotorists can expect flagged lane closures on SR 669 for chip seal.until Nov 13
- One lane, alternatingEastboundMotorists can expect flagged lane closures on SR 669 for chip seal.until Nov 13
SR-681 3 work zones
- Lanes open, work nearbyWestboundIntermittent flagging with signs for truck crossing (SR 681)until Nov 1
- Lanes open, work nearbyEastboundFlaggers in place for multiple slope stabilization locations (SR 681)until Apr 21
- Lanes open, work nearbyEastboundIntermittent flagging with signs for truck crossing (SR 681)until Nov 1
SR-730 1 work zone
- Lanes closedNorthboundA chip-seal paving project on S.R. 730, between Sprague Road and Nelson Avenue. Construction will begin on or after June 1, and throughout the project, traffic will be maintained in one lane with the use of flaggers and/or other traffic control devices. (W TRUESDELL ST)until Nov 1
SR-733 2 work zones
- Lanes closedWestboundIntermittent lane and shoulder closures in each direction with drums for sign replacements (SR 733)until Nov 30
- Lanes closedEastboundIntermittent lane and shoulder closures in each direction with drums for sign replacements (SR 733)until Nov 30
SR-741 2 work zones
- Lanes closedSouthboundSR 741 at I-75 will be subject to lane restrictions between from starting Wednesday, September 9 through October 2026. Crews will be repairing the roadway/bridge overhead. (SPRINGBORO PIKE)until Nov 6
- Lanes closedNorthboundSR 741 at I-75 will be subject to lane restrictions between from starting Wednesday, September 9 through October 2026. Crews will be repairing the roadway/bridge overhead. (SPRINGBORO PIKE)until Nov 6
SR-833 1 work zone
- Lanes closedNorthboundIntermittent lane and shoulder closures in each direction with drums for sign replacements (SR 833)until Nov 30
SR-850 2 work zones
- Road closedNorthboundRoad closed for widening project (SR 850)until Nov 6
- Road closedSouthboundRoad closed for widening project (SR 850)until Nov 6
Local roads
Local roads 137 work zones
- Lanes open, work nearbyNorthboundOne lane of traffic is maintained with flaggers. The completion date is September 30, 2026. (AMSTERDAM RD)until Nov 30
- Road closedEastboundBanner School Road access to/from U.S. Route 24 will be permanently closed beginning Friday, September 25. Use CR 17D or Independence Road. (BANNER SCHOOL RD)until Jun 30
- Road closedWestboundBanner School Road access to/from U.S. Route 24 will be permanently closed beginning Friday, September 25. Use CR 17D or Independence Road. (BANNER SCHOOL RD)until Jun 30
- Road closedSouthboundThe Barnhill Road bridge over U.S. 250 is currently closed due to damage. A vehicle traveling on U.S. 250 struck the bridge beams, causing the damage. ODOT is working on plans for permanent repairs, but an exact timeline is not yet available. An exact timeline is not yet available. (BARNHILL RD)until Oct 1
- Road closedSouthboundCR 118 (Bent Creek) will be permanently closed at SR 243 south. This closure is necessary to construct a new tie-in from CR 118 (Bent Creek) to CR 69 (Indian Guyan Rd). During this time, access to CR 118 (Bent Creek) will only be available via CR 2 (Greasy Ridge). (BENT CREEK RD)until Nov 3
- Lanes closedNorthboundBerea Rd. under I-90 will have various lane closures through October 2028. (BEREA RD)until Oct 1
- Lanes closedSouthboundBerea Rd. under I-90 will have various lane closures through October 2028. (BEREA RD)until Oct 1
- Road closedEastboundA bridge rehabilitation project on Branch Hill Miamiville Road over I-275. Branch Hill Miamiville Road will be closed through mid-September, and while the route is closed, motorists will be detoured by way of S.R. 126, Wards Corner Road and Branch Hill Guinea Pike. (BRANCH HILL MIAMIVILLE RD)until Nov 30
- Lanes closedNorthboundBrice Rd. over I-70 will be reduced to one lane in each direction starting Saturday, August 2. Two left turn lanes on Brice Rd. northbound to I-70 WB will be maintained. (BRICE RD)until Apr 30
- Lanes closedSouthboundBrice Rd. over I-70 will be reduced to one lane in each direction starting Saturday, August 2. Two left turn lanes on Brice Rd. northbound to I-70 WB will be maintained. (BRICE RD)until Apr 30
- Lanes open, work nearbyNorthboundConstruction of safe pedestrian and bicycle connections b/t the Little Miami Scenic Trail and the new Shawnee Interceptive Education Center. (BRUSH ROW RD)until Jun 1
- Lanes open, work nearbyEastboundExpect intermittent lane closures on Campbell Road in both directions at I-75 from Tuesday, March 4 through December 2025. Crews will be replacing the bridge. (CAMPBELL RD)until Dec 18
- Road closedWestboundThe E. 22nd St. and Cedar Ave. bridges over I-90 will be closed beginning Sunday, November 1, through fall 2027. (CEDAR AVE)until Nov 1
- Road closedEastboundThe E. 22nd St. and Cedar Ave. bridges over I-90 will be closed beginning Sunday, November 1, through fall 2027. (CEDAR AVE)until Nov 1
- Lanes open, work nearbyEastboundThe roadway has reopened to traffic. Motorist should anticipate short intermittent lane closures with flaggers. (CINCINNATI-ZANESVILLE RD)until Nov 1
- Lanes closedEastboundThe pedestrian bridge over I-75, between Section Road and City Centre Drive, is closed for reconstruction. Users will be detoured via Summit and Paddock roads. (CITYCENTRE DR)until Sep 30
- Lanes closedEastboundA widening project at the intersection of Clough Pike and Newtown Road intersection, with the construction turn lanes on Clough Pike, as well as a sidewalk on the south side of Clough Pike, between Copperleaf Lane and Newtown Road. Traffic will be maintained by flaggers during daytime hours of operation, daily from approximately 8 a.m. to 4 p.m. (CLOUGH RD)until Nov 20
- Road closedEastboundclosed on Aug. 31 permanently for cul-de-sac construction (COLE DR)until Mar 31
- Road closedWestboundclosed on Aug. 31 permanently for cul-de-sac construction (COLE DR)until Mar 31
- Lanes open, work nearbyEastboundThe roadway is open to traffic. Motorist should expect occasional lane closures with flaggers. Estimated project completion is November 2026. (COONPATH RD)until Nov 1
- Road closedSouthboundCounty Road 17 access to/from U.S. Route 24 will be permanently closed beginning Friday, September 25. Use CR 17D.until Jun 30
- Road closedNorthboundCounty Road 17 access to/from U.S. Route 24 will be permanently closed beginning Friday, September 25. Use CR 17D.until Jun 30
- Road closedEastboundclosed for widening to add a turn lane. (CR 4)until Nov 13
- Road closedEastboundclosed for widening to add a turn lane. (CR 4)until Nov 13
- Road closedWestboundclosed for widening to add a turn lane. (CR 4)until Nov 13
- Road closedWestboundclosed for widening to add a turn lane. (CR 4)until Nov 13
- Lanes closedNorthboundA bridge replacement, widening and turn-lane addition project on Dry Fork Road over I-74 at Harrison. Dry Fork Road will be subject to a 150-day closure beginning Monday, July 13, and motorists will be detoured via West and Harrison roads. The ramps will also be subject to intermittent, alternating closures at various times. (DRY FORK RD)until May 31
- Road closedNorthboundThe E. 22nd St. and Cedar Ave. bridges over I-90 will be closed beginning Sunday, November 1, through fall 2027. (E 22ND ST)until Nov 1
- Road closedSouthboundThe E. 22nd St. and Cedar Ave. bridges over I-90 will be closed beginning Sunday, November 1, through fall 2027. (E 22ND ST)until Nov 1
- Road closedEastboundCleveland Street will be closed for 75 days due to bridge rehabilitation. (E CLEVELAND ST)until Nov 13
- Road closedWestboundCleveland Street will be closed for 75 days due to bridge rehabilitation. (E CLEVELAND ST)until Nov 13
- Lanes open, work nearbyWestboundThe intersection of Highland Rd. and Valley View Rd. has various lane restrictions for drainage repairs through late March. Estimated completion, December 2026. (E HIGHLAND RD)until Dec 1
- Lanes closedEastboundEastbound lane closed for drainage work and turn-lane construction for new gas station construction (E LINCOLN HWY)until Nov 6
- Lanes closedWestboundTraffic will be maintained in a minimum of one lane in either direction and with traffic control devices and/or flaggers. (E MARKET ST)until Nov 30
- One lane, alternatingEastboundResurfacing work. Traffic is maintained with flaggers throughout the construction period. (E STATE ST)until Nov 30
- Road closedNorthboundConstruction of a roundabout at the intersection of Hutchinson and Ebenezer roads. Beginning July 6, the intersection will be closed, and Ebenezer Road motorists will be detoured locally by way of Bridgetown, Taylor, Rybolt, and Wessleman roads. Hutchinson Road motorists will be detoured by way of Filview Circle, Harrison Avenue, Race Road, Bridgetown Road and Ebenezer Road. (EBENEZER RD)until Nov 20
- Road closedWestboundWestbound Flory Road access to US 24 is permanently closed. Eastbound Jewell Road access to US 24 is permanently closed. (FLORY RD)until Dec 31
- Road closedEastboundEffective February 12, Gest Street will be closed between Freeman Avenue and 7th Street for water line replacement as part of the Brent Spence Bridge Corridor (Phase 3) project. Once closed, westbound motorists will be detoured via Linn Street, 8th Street and Freeman Avenue; eastbound motorists will be detoured via Freeman and 8th Street. (GEST ST)until Jun 30
- Lanes open, work nearbyEastboundGirdled Rd. at SR 44 will have various lane restrictions through November. (GIRDLED RD)until Nov 20
- Lanes open, work nearbyWestboundGirdled Rd. at SR 44 will have various lane restrictions through November. (GIRDLED RD)until Nov 20
And 97 more on local roads.
From the Ohio Department of Transportation's work zone feed (WZDx), as Orbit keeps it. Closures can change at short notice; follow the signs on the road. Some work zones come with few details from ODOT.